What to Include in an Architectural Metalwork RFQ

The quality of an RFQ sets the ceiling on the quality of the quotation it gets back. What a fabricator needs to price custom metalwork accurately — and what vague requests actually cost.

Custom brass screen metalwork representative of an RFQ scope element

The RFQ sets the ceiling

A fabricator can only quote as well as the request informs. A complete architectural metalwork RFQ produces a comparable, committed price with a defined scope; a vague one produces either a padded number with risk allowances buried in it, or a low number that changes later. The gap between those outcomes is not the fabricator's attitude — it is the information.
This article sets out what a strong RFQ for custom architectural metalwork contains, why each element changes the price, and how the missing pieces resurface as cost.

The core information set

1. Design drawings or intent. The single biggest price driver. Dimensioned drawings let a fabricator decompose the design into components; concept sketches require them to assume a decomposition and price its risk. For bespoke work, even an indicative drawing set with key dimensions and material zones dramatically sharpens the number. What fabricators do with those drawings — the shop drawing development that follows — is covered in how architectural metal shop drawings are developed.
2. Scope list. Element by element: screens, frames, cladding, railings, counters, displays, furniture. Quantity per element, and whether quantities are fixed or indicative. The list anchors everything — a package quoted per element can be tracked per element.
3. Materials. Grade where known — SS304, SS316, brass, aluminium — or a request for recommendation with the exposure environment described (interior, exterior, coastal, pool). The interior/exterior line alone changes material pricing materially: SS304 vs SS316 explains the trade.
4. Finishes. Mirror, brushed, textured, PVD colours, paint — with the finish per element where the design varies. Finish affects labour more than material: mirror polishing dominates the hours on polished work, and multi-finish packages add coordination. The colour-consistency machinery behind large PVD orders is described in PVD batch acceptance and sampling.
5. Project timeline. Award date, fabrication window, required delivery date, and site sequence if known. Schedule compression is real cost — overtime, expedited finishing, air freight — and it prices differently when known upfront versus discovered mid-project.
6. Site and logistics context. Where the project is, who receives the goods, and whether installation is by others. Delivery terms (EXW, FOB, DDP) with the destination port or address. Overseas metalwork has a whole packing and container engineering layer — covered in how large decorative metalwork is packed for overseas projects.
7. The special requirements. Anything unusual: glass or stone interfaces, lighting integration, acoustic or fire considerations, mock-up requirements, sample approval rounds, third-party inspection. Every one of these is legitimate; none of them prices itself.

What vague RFQs actually cost

When information is missing, fabricators do one of two things — and both cost the project:
  • They price the risk. Assumptions get covered with allowances: heavier material, more finishing hours, schedule buffers. The quote reads high and the buyer never learns which assumption drove it.
  • They price the hope. The number comes back attractive, and the assumptions surface as variations after award — at which point they price at their worst, under time pressure, mid-fabrication.
Either way, the information gap is paid for. The difference is only whether it is paid at quotation (comparable, negotiable) or after award (committed, urgent).

An RFQ quality checklist

Before sending a metalwork enquiry, check it against this list:
  1. Drawings attached, or intent drawings with a request for shop-drawing development
  1. Element-by-element scope with quantities
  1. Material grade, or environment description requesting recommendation
  1. Finish per element, with finish samples expected
  1. Timeline: award, fabrication window, delivery
  1. Destination and delivery terms
  1. Interfaces named (glass, stone, joinery, lighting) with responsible party where known
  1. Sample, mock-up or inspection requirements stated
An RFQ that clears these eight lines gets back quotes that can be compared line to line — and a first conversation that starts at engineering rather than at archaeology.

What happens at the fabricator's end

At KingDeco, an RFQ enters a technical review: drawings studied, scope decomposed, materials and finishes checked against workshop process, interfaces identified, and open questions returned — before any number is committed. That review is the same discipline described in sourcing custom architectural metalwork from China. Packages built on reviewed drawings price as built; packages built on assumptions price as hoped.
If you are preparing a metalwork package, the fastest accurate route is simple: send us your drawings for a technical review and quotation — and if the drawing set is not there yet, send what exists and ask the questions back.

MORE FROM THE GUIDE

Keep reading.

More practical guides on specifying architectural metalwork.

12 paiza restaurant the londoner

Next step

PLANNING A METALWORK PROJECT?

Discuss your requirements with KingDeco — drawings, finishes, quantities and schedule.

What happens next

We review your drawings and reply with technical questions, budget guidance or a quotation.

REQUEST A QUOTE